Project Update

Project updates for week of July 9, 2010

  • Framing and pouring footings and grade beams.
  • Tunnel walls to ATC are complete along with slab. Elevated slab for tunnel roof is being formed.
  • Underslab mechanical/electrical/plumbing (MEP) is progressing well with the recent dry weather.
  • Mason is mobilizing to start stair shafts.

Features

  • Location: Main Campus
  • 57,000 square feet (triples the square footage of the current library)
  • 14 private study rooms
  • Three large classrooms for library instruction
  • The “Write Place”
  • Technology center with more than 60 computers
  • Cyber Café
  • Two-story, quiet study area
  • Expanded tutoring center

Estimated Project Schedule

Time Table
Timeline(image)
April 7th
2009
Fall
2009
Winter
2009
Spring
2010
Summer
2012
Voters of District
509 approved a
$178M bond
referendum
Design and
development
phase
Commence bid
and award
period
Construction
start date
Anticipated
completion date