Project updates for week of July 9, 2010
- Concrete footings nearly complete.
- Concrete foundation walls nearly 90% complete.
- Two masonry stair shafts to be complete by the end of the week.
- Elevator hydraulic jack holes for all four elevators are complete.
- Concrete slab work to start in earnest next week.
- Below slab mechanical/electrical/plumbing work is progressing.
- Large crane for erection of structural steel to be assembled next week. Structural steel erection schedule for week of 7/19/10.
- Bioswale area built near Spartan Lake.
Features
- Location: Main Campus
- 130,000 square feet
- 29 new classrooms/labs/teaching spaces
- State-of-the-art healthcare training facilities
- The new HCC gives the college the opportunity to introduce new programs
- The second floor of the building will be the new home for the life sciences/biology
- Main entrance and welcome center
- Building contains room for growth and development of new programs
Estimated Project Schedule