Construction Projects on the Way
The affirmation of voters on April 7, 2009 allows ECC to further its mission of improving people’s lives through learning.
Facilities Master Plan
To meet the increasing demand for hire-ready students in high-demand fields, more classrooms, labs, and student spaces are needed. The ECC Board of Trustees adopted the ECC Facilities Master Plan, which centers on the construction of a mixture of new buildings and renovation of existing facilities.
Approximately 4,000 new jobs will be created through Master Plan construction projects and more than $530 million will be infused into the regional economy. ECC is committed to transparency and fiscal responsibility. This means consistently maintaining a balanced budget and completing capital projects on time and within the allotted budget. No referendum dollars will be used for college operating expenses. View business opportunities
Facilities Master Plan Current Timeline
Note: This is a living timeline and will be revised as more information becomes available.
- April 7, 2009 – Voters of District 509 approved a $178M bond referendum
- June 2009 – Approval of financial advisor
- Summer 2009 – Approval of the Academic Library and Learning Center, Student Resource Center Renovation and HCCOE to continue beyond schematic design
- Fall/Winter 2009-10 – Request for Proposal (RFP) for the Regional Public Safety Training Facility issued to local municipalities
- Spring 2010 – Proposed start of construction of Academic Library and Learning Center, Student Resource Center Renovation and HCCOE
- Summer 2012 – Anticipated completion of Academic Library and Learning Center, Student Resource Center Renovation and HCCOE